TRC America Demolition Services, Inc.
purchased the assets of the Hooker’s Point Power Plant to include 5
steam turbines and generators from 40 to 80 megawatt.
During phase one of
the project, we worked with the facility environmental personnel to
determine and test any potential environmental issues associated with
this project. Our personnel oversaw the testing of equipment and
associated piping to determine if any asbestos issues were present.
After the results were reviewed, TRC America Demolition Services contracted with a qualified company
to abate the detected asbestos and supplied our customer with the proper
documentation for removal and disposal.
During phase two we
disassembled/ dismantled the turbines and generators along with 5
condensers, feed water heaters and pumps. As part of this phase, our
crews dismantled/removed the complete substation for the facility to
include all associated cable, buss, cable trays, transformers, oil
filled circuit breakers and miscellaneous electrical gear. TRC America Demolition Services
worked closely with the facility owner to schedule the equipment removal
to meet set time requirements.
Our cutting crews
cut in excess of 2.5 million pounds of steel and cast iron that in some
cases exceeded 8” thick material. As part of TRC America Demolition Services' policy of maximizing
the recoverable materials on our projects, we recycled 99% of all
material removed from this facility to include copper, nickel, brass,
steel, etc. Our crews have been trained to sort materials to provide the
greatest return and have access to alloy testers if needed.